Select Date Home
Transmission Elements Outage Report for 15-01-2017

A. Details of Transmission Elements under Planned Outage:-
S.NoElement NameTypeVoltage LevelOwnerOutageRevivalExpected Date of RevivalReason / Remarks
DateTimeDateTime
1Anta RS 1500 MVA ICT 1ICT765/400 kVRRVPNL13-01-201711:4515-01-201720:14-Commissioning & synchronizing of RPH 2 Relay on ICT Bank 1
2Baspa(HP)-Karchamwangtoo(JP) 2Line400 kVJPHYDRO13-12-201608:42**16-01-2017For testing of line protection and GIS Maintenance at K.Wangtoo HEP.
3Sarnath(UP)-Varanasi(PG) 1Line400 kVPGCIL11-01-201714:03**NADue to overrloading of Anpara-Sarnath line
4Roorkee(PG)-Saharanpur(PG) 1Line400 kVPGCIL14-01-201711:08**16-01-2017For OPGW splicing work at LILO Point ( this line to be LILOED at Dehradun very soon)
5Baspa(HP)-Karchamwangtoo(JP) 1Line400 kVJPHYDRO14-01-201722:1815-01-201707:02-For rectification of ckt-2( which is out since 13.12.16 due feeder -2 fault in GIS Baspa)
6Daultabad(HVPNL)-Gurgaon(PG) -2Line400 kVHVPNL15-01-201709:4215-01-201716:24-Planned annual maintenanceTree cutting and General maintenance in the line and sub-station yards by HVPNL
7Amritsar(PG)-Makhu(PSEB) -1Line400 kVPSEB15-01-201710:57**16-01-2017Diverson of Linefor String/sagging works of shifting of 7 nos. Towers, due to 4- laning works near Harike By pass Road by PSTL
8Amritsar(PG)-Makhu(PSEB) -2Line400 kVPSEB15-01-201710:57**16-01-2017Diverson of Linefor String/sagging works of shifting of 7 nos. Towers, due to 4- laning works near Harike By pass Road by PSTL
9Dehar 250 MVA ICTICT400/220 kVBBMB15-10-201608:02**16-01-2017Construction of new element For replacement of 400/220 ,250 MVA ICT (3*83.3 MVA + one spare unit 83.3 MVA) and its associate bay equipments with 315 MVA ICT (3*105 MVA + I spare unit 105 MVA) Transformers of 400/220 KV CGL make under Northern Region Strengthening Scheme at BBMB Dehar.The replacement work will be carried out by PGCIL.
10Dhuri(400) 500 MVA ICT 2ICT400/220 kVPSEB17-11-201610:26**NAFor Complete internal inspection due to Detection of high C2H2 from the test result of PD test conducted at site
11Dadri 500 MVA ICT 2ICT400/220 kVNTPC09-01-201710:02**NABushing oil leakage
12Kashipur 315 MVA ICT 1ICT400/220 kVUPCL11-01-201710:36**16-01-2017For performing Tan Delta testing of transformer , tightening of clamps,routine testing, preventive maintenance.
13G.Noida 315 MVA ICT 3ICT400/220 kVUPPTCL11-01-201710:40**04-02-2017Replacement of transformer-- For replacement/retrofittment of this 315MVA ICT-3 with new 500MVA ICT.
14New Wanpoh 125 MVAR B/Reactor 1Bus Reactor400 kVPGCIL10-10-201610:09**NATake out due to low voltage.
15panipat-Dhulkote 1Line220 kVBBMB02-01-201709:36**16-01-2017To take line reactor Out of serviceFor replacement of old conductor with new conductor for capacity enhancement by BBMB.
16Khurja(UP)-Napp(NPC) 2Line220 kVUPPTCL15-01-201708:2015-01-201719:33-Polymer insulator replacement-- For replacement of porcelain disc insulators with polymer insulators strings in the line by UPPTCL.
17AD Hydro(ADHY)-Nallagarh(PG) 1Line220 kVADHYDRO15-01-201710:5015-01-201717:04-Planned annual maintenance-- preventive maintenance and cleaning of disc insulators etc by ADH Power ltd.
18FSC of Pampore-1 at KishnprFSC220 kVPGCIL30-10-201212:00**NALine length has reduced after LILO work completion
19FSC of Pampore-2 at KishnprFSC220 kVPGCIL30-10-201212:00**NALine length has reduced after LILO work completion
*-Line still under outage     NA - Not Available

B. Details of Transmission Elements under Forced Outage:-
S.NoElement NameTypeVoltage LevelOwnerOutageRevivalExpected Date of RevivalReason / Remarks
DateTimeDateTime
1Jatikala-Kanpur NewLine765 kVPGCIL15-01-201701:4915-01-201705:55-.
2Meerut 1500 MVA ICT 2ICT765/400 kVPGCIL12-01-201712:36**NAfor tap changing 9 to 11
3G.Noida 765 (3*80) 240 MVAR (765kV) Bus Reactor 1Bus Reactor765 kVUPPTCL06-08-201610:32**NATo attend Buchholz alarm in R phase
4Mainpuri 765(UP) 765 kV Bus 2BUS765 kVUPPTCL14-01-201716:1915-01-201713:09-24 Hrs monitoring of 1000 MVA 765/400 KV ICT at Mainpur.
5Bamnauli(DTL)-Jatikala(PG) 1Line400 kVDTL22-05-201620:29**NATower damage (First dead end tower from Bamnauli S/S) / Ckt-II charge through ERS tower
6Kurukshetra(PG)-Malerkotla(PG) 2Line400 kVNRSS31B11-01-201711:0515-01-201710:34-Problem in GIS at Malerkotla
7Kurukshetra(PG)-Malerkotla(PG) 1Line400 kVNRSS31B11-01-201711:0515-01-201709:57-Problem in GIS at Malerkotla
8Gorakhpur(PG)-Lucknow(PG) 2Line400 kVPLINK15-01-201701:2015-01-201708:40-.
9Bhilwara(PG)-Chabra(RVPNL)Line400 kVRRVPNL15-01-201707:0315-01-201708:02-Phase to earth fault.
10Akal-Jodhpur IILine400 kVRRVPNL15-01-201713:1815-01-201721:01-Phase to earth fault.
11Khedar-Nuhiyawali 2Line400 kVHVPNL15-01-201713:4415-01-201718:44-Tripping due to earth fault.
12Kurukshetra(PG)-Malerkotla(PG) 2Line400 kVNRSS31B15-01-201721:1015-01-201722:35-Auto reclosed.
13Kalisindh 315 MVA ICTICT400/220 kVRRVPNL04-06-201615:50**NABuchholz relay operated.
14Bawana 315 MVA ICT 1ICT400/220 kVDTL11-12-201608:37**NAFire in ICT-1
15Jodhpur II 315 MVA ICT 2ICT400/220 kVRRVPNL24-12-201614:11**NAR-ph HV side bushing burst.
16Sultanpur 240 MVA ICT 2ICT400/220 kVUPPTCL12-01-201710:11**NATo attend hot spot on R&Y phase isolator clamps
17Makhu 315 MVA ICT 2ICT400/220 kVPSEB14-01-201720:40**NATripped on High voltage.
18 Bareilly 50 MVAR B/RBus Reactor400 kVUPPTCL05-08-200700:00**NAFailure of Reactor.
19 Sarnath 50 MVAR B/RBus Reactor400 kVUPPTCL16-02-200906:14**NAFailure of Reactor.
20FSC of Bareilly-I at UnnaoFSC400 kVPGCIL19-04-201513:10**NAFire in FSC.
21Wagoora 50 MVAR B/RBus Reactor400 kVPGCIL22-04-201518:56**NATake out due to low voltage.
22FSC ( 50% ) of Koteshwar Pool -2 at Meerut (PG)FSC400 kVPGCIL16-07-201513:01**NAFire in FSC-2 at Meerut.
23FACT at BLB in Knp-BLB LineFACTS400 kVPGCIL02-07-201610:20**NAY-Phase current imbalance
24Fatehpur(UP)-Unchahar(NTPC) 2Line220 kVUPPTCL15-01-201704:1215-01-201710:50-BKR hydraulic pump was continuously running and adequate pressure not developing
25Mandola(PG)-Wazirabad(DTL) 3Line220 kVDTL15-01-201722:0316-01-201706:55-.
*-Line still under outage     NA - Not Available

C. Details of Transmission Elements Opened manually due to High Voltage:-
S.NoElement NameTypeVoltage LevelOwnerOutageRevivalRemarks
DateTimeDateTime
1Meerut - MogaLine765 kVPGCIL14-01-201720:1015-01-201707:08 
2Bhiwani -MeerutLine765 kVPGCIL14-01-201721:0615-01-201707:05 
3Agra-Fatehpur 2Line765 kVPGCIL15-01-201700:0215-01-201707:16 
4Bhiwani -MeerutLine765 kVPGCIL15-01-201720:1916-01-201708:35 
5Meerut - MogaLine765 kVPGCIL15-01-201723:3916-01-201707:30 
6Bhiwani-Jind 1Line400 kVPGCIL31-12-201601:39**** 
7Ratangarh-Suratgarh 2Line400 kVRRVPNL03-01-201704:42**** 
8Bassi-Bhiwadi 2Line400 kVPGCIL13-01-201720:5215-01-201709:36 
9Chamera pool-Jalandhar 2Line400 kVPGCIL13-01-201721:31**** 
10Abdullapur-Kurukshetra(PG) 1Line400 kVPGCIL13-01-201722:1315-01-201709:31 
11Amritsar(PG)-Makhu(PSEB) -1Line400 kVPSEB14-01-201700:28**** 
12Hisar-Kaithal 1Line400 kVPGCIL14-01-201702:1515-01-201709:58 
13Ajmer II-DidwanaLine400 kVRRVPNL14-01-201713:2216-01-201706:29 
14Bikaner-Didwana 1Line400 kVRRVPNL14-01-201717:3216-01-201707:36 
15Merta-RatangarhLine400 kVRRVPNL14-01-201718:5415-01-201707:45 
16Kota(PG)-Merta(RVPNL) 1Line400 kVPGCIL14-01-201718:5815-01-201707:56 
17Jodhpur II-Merta 1Line400 kVRRVPNL14-01-201719:5015-01-201720:41 
18Agra-Sikar 1Line400 kVPGCIL14-01-201720:0415-01-201709:19 
19Agra-Bhiwadi 2Line400 kVPGCIL14-01-201720:0615-01-201709:04 
20Bhiwadi-Neemrana 1Line400 kVPGCIL14-01-201720:1015-01-201709:08 
21Chamera I(NHPC)-Jalandhar(PG) 2Line400 kVPGCIL14-01-201720:1016-01-201708:09 
22Ratangarh (RVPNL) - Sikar (PG) - 1Line400 kVPGCIL14-01-201720:1115-01-201707:54 
23Jhakri-Panchkula 2Line400 kVPGCIL14-01-201720:2115-01-201705:26 
24Jhakri(SJVNL)-Karchamwangtoo(JP) 1Line400 kVJPHYDRO14-01-201720:2415-01-201705:14 
25Koldam(NTPC)-Ludhiana(PG) -2Line400 kVPKTCL14-01-201721:0215-01-201705:44 
26Nallagarh-Patiala 2Line400 kVPGCIL14-01-201721:0415-01-201705:18 
27Abdullapur-Karchamwangtoo 2Line400 kVJPL14-01-201721:0415-01-201705:29 
28Ballabgarh-Mainpuri 2Line400 kVPGCIL14-01-201721:0815-01-201707:19 
29Fatehpur-Mainpuri 2Line400 kVPGCIL14-01-201721:0915-01-201707:20 
30Agra(PG)-Auraiya(NTPC) 2Line400 kVPGCIL14-01-201721:1115-01-201709:12 
31Ballabgarh-Kanpur 2Line400 kVPGCIL14-01-201721:1115-01-201707:28 
32Agra-Jaipur South-1Line400 kVPGCIL14-01-201721:1315-01-201709:31 
33Nallagarh(PG)-Rampur(SJVNL) -1Line400 kVPGCIL14-01-201721:2715-01-201705:29 
34Nallagarh(PG)-Parbati Pool(PG)Line400 kVPKTCL14-01-201721:3115-01-201709:32 
35Abdullapur-Panchkula 1Line400 kVPGCIL14-01-201721:3415-01-201705:32 
36Chamera pool-Jalandhar 1Line400 kVPGCIL14-01-201721:3415-01-201705:39 
37Jalandhar-Kurukshetra(PG) 1Line400 kVPGCIL14-01-201721:3715-01-201709:32 
38Amritsar-Parb-pol 1Line400 kVPGCIL14-01-201721:3715-01-201709:30 
39Fatehabad-HisarLine400 kVPGCIL14-01-201721:5315-01-201709:56 
40Ballabgarh(PG)-Bamnauli(DTL) 2Line400 kVDTL14-01-201722:3115-01-201707:42 
41Gorakhpur(PG)-Lucknow(PG) 1Line400 kVPLINK15-01-201701:2015-01-201708:40 
42Heerapura-MertaLine400 kVRRVPNL15-01-201704:1415-01-201707:51 
43Ratangarh (RVPNL) - Sikar (PG) - 2Line400 kVPGCIL15-01-201709:0015-01-201709:14 
44Agra-Bhiwadi 2Line400 kVPGCIL15-01-201719:1316-01-201706:21 
45Bhiwadi-Neemrana 1Line400 kVPGCIL15-01-201719:1616-01-201706:37 
46Agra-Sikar 1Line400 kVPGCIL15-01-201719:3416-01-201708:26 
47Fatehabad-HisarLine400 kVPGCIL15-01-201719:3416-01-201708:58 
48Agra-Jaipur South-1Line400 kVPGCIL15-01-201719:3516-01-201706:42 
49Jalandhar-Kurukshetra(PG) 1Line400 kVPGCIL15-01-201719:5916-01-201712:52 
50Abdullapur-Panchkula 2Line400 kVPGCIL15-01-201720:0516-01-201706:05 
51Merta-RatangarhLine400 kVRRVPNL15-01-201720:0616-01-201706:13 
52Nallagarh-Patiala 2Line400 kVPGCIL15-01-201720:1116-01-201707:58 
53Ratangarh (RVPNL) - Sikar (PG) - 1Line400 kVPGCIL15-01-201720:1516-01-201706:32 
54Jhakri(SJVNL)-Karchamwangtoo(JP) 2Line400 kVJPHYDRO15-01-201720:1516-01-201705:28 
55Nallagarh(PG)-Parbati Pool(PG)Line400 kVPKTCL15-01-201720:1716-01-201708:45 
56Jhakri-Panchkula 2Line400 kVPGCIL15-01-201720:1716-01-201706:02 
57Kurukshetra(PG)-Sonipat 1Line400 kVPGCIL15-01-201720:1916-01-201709:11 
58Amritsar-Parb-pol 1Line400 kVPGCIL15-01-201721:2416-01-201710:26 
59Abdullapur-Karchamwangtoo 1Line400 kVJPL15-01-201721:2716-01-201705:45 
60Koldam(NTPC)-Ludhiana(PG) -2Line400 kVPKTCL15-01-201721:2816-01-201707:22 
61Ballabgarh-Kanpur 3Line400 kVPGCIL15-01-201721:2916-01-201707:22 
62Bhiwadi-HisarLine400 kVPGCIL15-01-201721:3116-01-201709:53 
63Ballabgarh(PG)-Bamnauli(DTL) 1Line400 kVDTL15-01-201722:0216-01-201706:56 
64Baspa(HP)-Karchamwangtoo(JP) 1Line400 kVJPHYDRO15-01-201722:16**** 
65Chamera pool-Jalandhar 1Line400 kVPGCIL15-01-201723:0416-01-201710:53 
66Mukatsar -Talwandi Sabo - 1Line400 kVPSEB15-01-201723:1016-01-201708:51 
67Makhu -Mukatsar -1Line400 kVPSEB15-01-201723:1216-01-201708:50 
68Makhu -Nakodar -1Line400 kVPSEB15-01-201723:1416-01-201708:10 
69Fatehpur-Mainpuri 2Line400 kVPGCIL15-01-201723:3516-01-201707:38 
70Jalandhar-Moga 1Line400 kVPGCIL15-01-201723:3616-01-201713:21 
71Mandola-Meerut 1Line400 kVPGCIL15-01-201723:4116-01-201709:21 
72Koldam(NTPC)-Parbati Pool(PG) Line400 kVPKTCL15-01-201723:4516-01-201710:31 
73Agra-Bassi 1Line400 kVPGCIL15-01-201723:5516-01-201707:44 
74Ballabgarh-Kanpur 1Line400 kVPGCIL15-01-201723:59**** 
** - Line shall be closed subject to voltage permissibility